|
STATE ROAD 60, VERO BEACH, FLORIDA
Click image for larger view
THE CHALLENGE
Install 860’ LF of stormwater piping through
environmentally impacted areas along a major
thoroughfare and hurricane evacuation route for Florida
Department of Transportation, District 4.
THE ISSUES
• The stormwater piping must be lined to prevent
impacted groundwater from entering the stormwater
system and water shed areas.
• Install piping across roadways in 24 hours without
closing roadways.
• No disruptions to operating businesses, or impacts to
neighboring residences.
• Keep existing stormwater system fully operational until
new system is online.
|
THE SOLUTION
HCR’s experienced Heavy Construction Team analyzed the required
specifications and developed value engineering and cost effective
solutions which addressed all of FDOT’s concerns.
During the initial project evaluation HCR determined that lined concrete
piping was extremely expensive, (over $485,000), hard to handle and
very laborious to install. But HCR had the solution, use polyethylene
piping. One call determined that N-12 poly piping which is impervious
to infiltration and seepage (locks together water tight), is very easy to
handle and install (20’ lengths instead of standard 8’ lengths of RCP),
and approved by most DOT Departments resulting in a cost savings of
over $430,000.00 compared to using lined RCP.
Due to the seasonal high volume of traffic, closing the roadways for any period of time was not an option. HCR recommended the use of a Pilot Tube Jack and Bore (J&B) Method to install a length of casing under the road way. Using the pilot tube J&B is very precise over conventional J&B where the line and grade must be within prescribed tolerances. A 73” FDOT approved steel casing in 30’ sections were welded together then jacked a total of 160’ underneath the existing roadway. |
HCR roadway crews then pushed the 8 sections
of ADS N-12 poly piping through the casing to the
next structure. Working round the clock, HCR
crews along with our subcontractors took less
than 12 hours to complete this task.
HCR’s vast experience again proved this was the
most efficient and cost effective method with very
little disruption to traffic and the surrounding
areas.
A major factor during installation of the new stormwater system was keeping the existing drainage flowing at all times. Due to major inconveniences caused to residences during the rainy season in the form of flooding, HCR devised a coffer dam by pass system to keep the existing system operational as well as reducing the chance of flooding. Also 16” and 8” diesel powered centrifugal pumps (over 20,000 GPM) were used round the clock to ensure the drainage system canals were always flowing freely. |
|
|
|