Central Florida Wastewater Treatment Plant       Central Florida Wastewater Treatment Plant        

The Challenge

This wastewater treatment plant was discontinuing it’s waste-to-energy process and wanted to have their thickened waste activated sludge dewatered dry enough to send for composting. The total volume that Handex was asked to dewater was up to 80k gallons per day.

The Solution

Handex brought in a 21” bowl, tri canter, 3 phase , skid mounted centrifuge. Our engineers worked on permitting for electrical and also dug trenches to run electrical underground.

The Result

Handex has been successfully processing these biosolids 12 hours per day 6 days per week for over a year now and have been asked to continue to do so for two more years at a minimum.